Buying guide · For industrial, research and OEM buyers

How to Choose a Motion Platform

Most guides on this subject explain degrees of freedom and stop there. That is the easy part. The decisions that decide whether a motion platform project succeeds are procurement decisions: what order to make them in, how to tell a supplier who engineers from one who assembles, what belongs in the RFQ, and what you agree before signing rather than after delivery.

The short answer: define the physical job first, settle the architecture second, qualify suppliers third, send everyone the same RFQ fourth, compare quotations on scope before price, and write the acceptance criteria into the purchase order. Starting by comparing products — where most projects begin — means choosing before the question has been defined.

Buying guide  ·  Written by the CSCmotion Motion Control Engineering Team  ·  Updated October 5, 2026  ·  Reading time ~18 min

Six-step motion platform buying process: define requirements, choose architecture, qualify suppliers, issue comparable RFQs, compare scope, and agree acceptance before ordering.

Fig. 1 · Six decisions, two of them one-way. Most projects that go wrong took the right decisions in the wrong order.

2 of 6

Decisions you cannot reverse

Architecture at fabrication; acceptance at the order.

7

Questions

That separate a builder from an assembler.

12

Scope lines

To normalise before comparing any two quotations.

32

Point checklist

Five project phases, free, no email form.

Order of operations

The Buying Sequence, and Which Steps Cannot Be Undone

Motion platform projects go wrong far more often from sequence than from any single choice. Each step produces the input the next one needs, and two of them are locked for good — one when steel is cut, one when the order is signed.

The 6-Step Buying Sequence  Read the last column before skipping a step.

Step What you decide Reversible? What skipping it costs you
01 · Define the physical job What the platform must reproduce, test or move; gross moving load, CoG height, one combined trajectory, duty cycle Yes — and free to refine now Every quotation is sized against a different guess
02 · Settle the architecture Axis count and drive technology, from the motion requirement rather than the budget No — locked at fabrication A 3DOF platform cannot become 6DOF; there is no upgrade path
03 · Qualify the suppliers Who can engineer the platform, not just assemble one Yes, but costly after an order You compare datasheets from companies with different capabilities
04 · Issue a comparable RFQ Identical, complete information to every supplier, including scope boundary and acceptance expectation Yes — reissuing costs schedule Quotations arrive that cannot be compared, and you find out late
05 · Normalise and compare Every quotation adjusted to the same scope before price is read Until the order is placed You select the supplier who excluded the most
06 · Agree acceptance, then order Test load, trajectory, reference point, instrument, tolerance and record format, in writing Effectively no Acceptance gets negotiated after delivery, from the weakest position

What “cannot be undone” looks like: joint spacing, frame geometry and actuator mounting positions are cut into steel. At that point steps 01 and 02 stop being decisions and become the machine — which is why they are taken from the motion requirement, and why the 3DOF vs 6DOF and electric vs hydraulic guides come before any quotation.

Still at step 01? Send what you know about the load and the motion, and get back the list of inputs that are still missing.  Get your missing-inputs list →

The most useful hour in the whole process

Seven Questions That Separate Builders From Assemblers

Many companies selling motion platforms buy actuators, buy a controller and bolt them to a frame. That is a legitimate business, and for some projects it is enough. It is also a different capability from designing the mechanism, and you should know which one you are buying from. None of these questions can be answered from a catalogue.

The 7-Question Builder Test  Ask every supplier on your shortlist. Our own answers are in the last column, so you can hold us to them.

Ask this A builder answers with An assembler answers with How CSCmotion answers
01 · "Who set the attachment geometry, and against what requirement?" Joint circle radii, angular phase and the workspace trade-offs made "A standard Stewart configuration" Our engineers set the joint layout against your trajectory, and every 6DOF platform uses Cardan joints for a determinate load path
02 · "With my payload and trajectory, what peak actuator force results, and at which pose?" A dynamic solution — or the exact inputs needed first A figure from static payload alone Solved from your GML, CoG and trajectory before we quote
03 · "How do you verify structural and modal behaviour?" Named analyses, run on the real peak loads "The frame is very strong" Stiffness, buckling, modal and fatigue checks on the peak limb forces from the dynamic solution
04 · "Who wrote the motion control software, and can you change it?" "We did, and yes" The name of another company We write the kinematics and firmware and build the controller card; changes are a development task, not a support ticket
05 · "Is your accuracy figure measured or derived? With what instrument, at what load?" A load, a pose set, a reference point and an instrument Encoder resolution multiplied by a gear ratio Every figure we give states whether it is a design value or a measured result, and under which conditions
06 · "How do you correct for the difference between the drawing and the machine you built?" As-built geometry identified and compensated in the controller "Assembly is to tolerance" As-built geometry is identified and loaded into the controller before the loaded test
07 · "Can I see your factory acceptance test items before I order?" A written list, before the order An offer to write one later We propose the FAT items for your load case before you order; your team or SGS / BV are welcome to witness
How to use the answers. No question has a single correct reply, and “we need your mass properties before we can answer that” is a good answer, not a dodge. Listen for engineering vocabulary rather than sales vocabulary, and for whether the person can go one level deeper on a follow-up. That is usually clear within ten minutes.

Here is the honest version: an assembler or integrator can be the right supplier — for a catalogue-sized load case on a tight schedule, or when you need a turnkey simulator rather than a motion system. Ask the questions to know what you are buying, not to rule people out.

Want to rehearse the questions first? Try all seven on us before you use them on your shortlist. We answer each in writing.  Try the seven questions on us →

Make the responses comparable

What Belongs in a Motion Platform RFQ

An RFQ is not only for collecting prices. It is for collecting prices that can be compared, which means every supplier gets the same information and is told exactly what the quotation must cover. Where a term is used inconsistently across the industry, our glossary gives the definition we work to.

The 10-Line RFQ Ledger  The last column is what goes wrong when the line is missing.

Include What it means If you leave it out
Gross moving load Everything that moves: article, fixture, cabin, occupants, cabling, instrumentation Suppliers size against the payload alone, and the platform is under-rated
CoG height and inertia Height above the platform surface; Ixx, Iyy, Izz about the payload CoG Rotational demand is unknown, so every quotation carries hidden assumptions
One combined trajectory A realistic motion profile, not a list of per-axis maxima Suppliers quote against maxima that never occur together
Duty cycle Hours per day, continuous or intermittent, peak versus sustained Thermal rating cannot be set; actuators may be under-specified
Scope boundary Platform only, or platform plus integration, installation and training The single largest source of non-comparable quotations
Host interface Protocol, update rate, coordinate convention, who owns integration Interface work appears as a change order after the order
Acceptance expectation How the platform will be judged to meet the specification Acceptance is negotiated after delivery, from a weak position
Site constraints Ceiling height, floor loading, power supply, HVAC capacity, access route A platform that cannot be installed, or needs unbudgeted site work
Standards and compliance Any test standard, safety category or certification you need Requalification late in the project, or a platform that cannot be signed off
Schedule and milestones Required delivery date and any fixed intermediate dates Schedule risk is discovered rather than managed

Why the first two lines matter most: if gross moving load and CoG height are estimated rather than measured, the gap shows up at the loaded acceptance test — when the machine is already built. Weighing the moving assembly costs an afternoon. See Payload, Stroke & Acceleration for why CoG height multiplies the load.

Writing the technical half of the RFQ now? The Specification Builder formats it into one block and marks every unknown, instead of leaving it blank.  Generate your RFQ specification block →

Before you look at the numbers

Why Two Motion Platform Quotations Are Rarely Comparable

Quotations for the same platform often differ by a large factor, and the difference is usually scope rather than value. Normalise every quotation to the same twelve lines first, then compare price. The last column is how our own quotation answers each line, so you can normalise us too.

The 12-Line Scope Normaliser  Ask every supplier each question in the middle column.

Scope line Ask every supplier CSCmotion quotation
Motion controller Included, or priced separately? Whose hardware? Included — our own controller card
Control software licence Perpetual or subscription? How many seats? What happens at renewal? Included, with no separate subscription
API documentation Included and documented, or an extra licence? Included
Interface document Issued before integration starts, or at delivery? Included, issued before integration starts
Factory acceptance test Included, witnessed or remote? Under what load and trajectory? Test items proposed before order; witnessing welcome; scope confirmed at quotation
Packing and freight Which Incoterm? Who handles customs and inland delivery? Confirmed at quotation
Installation Performed, supervised, or documentation only? Confirmed at quotation
Commissioning and tuning On site, or remote support only? Confirmed at quotation
Training Operator, maintenance or both? How many people, where? Confirmed at quotation
Warranty Duration, coverage, response time, on-site or return? 12 months
Spares Recommended holding, lead time for critical parts, availability period Confirmed at quotation
Site works Foundation, anchoring, power and HVAC — whose scope? Confirmed at quotation

Lowest quote ≠ lowest cost.

The pattern to watch for: a quotation well below the others is worth investigating, not celebrating. Usually it covers the mechanism alone while the others cover a delivered, working system, and the gap comes back as change orders during integration — when you no longer have competitive leverage. Ask the low bidder which of the twelve lines are excluded.

Holding quotations that look nothing alike? Send them — ours included — and we mark which of the twelve lines each one leaves out.  Have your quotations normalised →

Where the money goes

What Actually Drives the Price of a Motion Platform

There is no meaningful list price for an engineered motion platform, and a supplier who quotes one before knowing your load and trajectory is quoting a different machine from the one you need. The cost drivers, though, are entirely predictable — and knowing them shows where savings hide.

The 6-Driver Cost Map  In rough order of influence.

Driver Why it costs Where the saving usually is
01 · Payload × acceleration Together they set peak actuator force, which sizes cylinders, motors, drives, structure and foundation An acceleration figure copied from an earlier project, never re-derived from this one
02 · Stroke and envelope Longer travel grows the whole machine: cylinders, neutral height, structure, footprint, ceiling Per-axis maxima the real trajectory never reaches
03 · Centre-of-gravity height It acts as a lever on the actuators; a tall payload needs more capability than its mass suggests Lowering the fixture or cabin floor — often the cheapest saving available
04 · Duty cycle Electric actuators are thermally limited; a full shift can need a larger rating at the same peak Stating duty honestly, rather than assuming the worst
05 · Precision requirement Tighter repeatability means better components, more calibration and longer acceptance Specifying what the application needs, not the best number available
06 · Integration and scope Custom interfaces, protocols, certification support and on-site commissioning add engineering hours A clear scope boundary in the RFQ

Where savings usually exist: in requirements nobody examined — a payload with a large unexplained margin, an acceleration from another project, travel at maxima the motion never uses. Re-deriving the requirement from what the platform will really do often shows a smaller machine is enough. That review costs nothing and belongs before any quotation.

Wondering which of your requirements is driving the cost? Send the specification, and an engineer tells you which line to question first.  Find your biggest cost driver →

Budget lines outside the quotation

Costs That Sit Outside the Platform Price<

None of these is unusual, and all of them are routinely discovered late. They belong in the project budget from day one.

The 8-Line Outside-the-Quote Ledger  Whose scope each line usually falls into.

Budget line Why it gets missed Usually owned by
Host integration labour Often the largest item after the platform itself, and the most underestimated You or your integrator
Foundation and anchoring Existing floors are not always adequate for dynamic loads Your site team, using load data from the supplier
HVAC capacity Electric servo drives reject heat into the room Your building services
Safety guarding and interlocks Perimeter guards, light curtains, gates and emergency stop circuits Often the integrator or end user
Access and rigging Door widths, corridor turns and crane access, found on delivery day Your site team
Spares holding Critical spares held locally against downtime You, on the supplier's recommendation
Training and ramp-up The productivity gap while a new system is learned Shared
Acceptance effort Your engineers' time to witness, review records and sign off You

Building the project budget? Ask for the foundation loads, heat load and power data your site team will need.  Request site planning data →

Agree it before the order

Motion Platform Acceptance Criteria and Project Risk

Acceptance is the only mechanism you have for confirming that what arrives matches what was specified. It has to be written before the purchase order, because after delivery the negotiating position is entirely different. “The platform moves as expected” is not a criterion — it cannot be failed, so it cannot be passed either.

The 6-Element Acceptance Statement  Every acceptance line in your RFQ needs all six.

Element What to write Why it has to be named
Test load The moving assembly, or a stated equivalent mass at a stated CoG An empty-platform result proves only that the mechanism moves
Trajectory The combined motion profile the platform must reproduce Single-axis tests hide the combined demand that loads the limbs
Reference point The point on the payload the motion is measured at Table centre is not the payload CoG; the numbers differ
Instrument What measures the motion, and how it is set up Two parties can measure the same platform and both be right
Tolerance The threshold for each measured quantity Without it, every result is open to interpretation
Record format What the signed FAT record contains It becomes the reference for warranty and future service

The 4-Risk Register  All four are avoidable at specification stage, and expensive afterwards.

Risk When it shows up Mitigation
01 · Under-specified moving load At commissioning, when the fixture and cabin weigh more than the RFQ said Weigh the assembly, include everything that moves, agree a margin now
02 · Interface mismatch At integration: platform and host disagree on convention, units, update rate or states Get the interface document before integration starts and have your host developer review it during build
03 · Acceptance never agreed At delivery, with no written definition of success Agree the FAT items during qualification and attach them to the purchase order
04 · Support dependency At the first fault, when the supplier must escalate to whoever made the actuator or controller Establish during qualification who makes the critical components and who owns the software

On risk 04, for transparency: we make our own servo electric cylinders, controller card and control software, so the escalation chain ends with us. We raise it because it is a real difference between suppliers that buyers rarely check — not because every project needs a vertically integrated supplier. If your shortlist includes integrators, ask who they escalate to and what the response commitment is.

Ready to write acceptance into the order? Send your load and trajectory, and we propose the FAT items before you sign.  Request proposed FAT items before ordering →

Take it with you

Motion Platform Procurement Checklist

Thirty-two items across the five phases above. Tick them off as you go, then download your progress or print it for the project file. It runs entirely in your browser — nothing is stored or sent, and there is no email form in front of it.

Phase 1 · Define the requirement

Complete before contacting any supplier.

Phase 2 · Settle the architecture

Locked once fabrication begins.

Phase 3 · Qualify suppliers

One conversation per supplier is usually enough.

Phase 4 · RFQ and comparison

Identical information to every supplier.

Phase 5 · Acceptance and budget

Agreed before the purchase order is issued.

Stuck on a Phase 1 line? Send what you have, and an engineer helps you fill the gaps before you go to market.  Get help completing Phase 1 →

Frequently asked

How to Choose a Motion Platform — FAQ

The procurement questions we hear most. Engineering questions are answered in the Technology guides; commercial ones in the FAQ.

There is no meaningful list price for an engineered motion platform, because cost follows gross moving load, acceleration, stroke, CoG height, duty cycle and precision rather than a model number. Payload multiplied by acceleration dominates, because it sets actuator force and therefore the size of every component. Price is confirmed at quotation, against your full specification.

Ask questions a catalogue cannot answer: the peak actuator force at your payload and the pose where it occurs, how the as-built geometry is compensated, who wrote the control software, and what the FAT will measure. An engineering company answers or tells you exactly which inputs it needs first. See the seven questions.

Because the scope boundary differs. One may include the controller, software, interface documentation, FAT, installation and training; another may quote the mechanism alone. Normalise every quotation to the same twelve scope lines before reading the price.

Host integration labour, usually the largest line after the platform itself. Then foundation and anchoring, HVAC for the heat electric drives reject, safety guarding and interlocks, access and rigging, spares, training, and your own engineers' time to witness acceptance.

An engineered platform passes through engineering review and design, manufacture, assembly, control integration and factory acceptance, then shipping, installation and commissioning. Adapting an existing configuration is much faster than new mechanism geometry. Lead time is confirmed at quotation; ask every supplier which phase carries the most schedule risk.

If a standard product meets your gross moving load, trajectory and duty with margin, buy it — it will normally be faster and cheaper, and we will say so ourselves. The trap is a standard platform that nearly fits: the shortfall appears at commissioning, when nothing can be changed. Check it against your combined trajectory, not per-axis maxima.

Yes. Our quotation includes our own controller card and control software with no separate subscription, plus API documentation and an interface document issued before integration starts. Installation, commissioning, training, freight terms and spares are confirmed at quotation; the warranty is 12 months.

An under-specified moving load found at commissioning, an interface mismatch with the host system, acceptance criteria never agreed, and support that depends on a component maker rather than the platform builder. All four are avoidable at specification stage and expensive afterwards.

Use us as a second opinion

Test This Guide on Us First

Early in a procurement and want to try the Phase 3 questions before using them on your shortlist? Ask us. We answer them properly — and if the honest answer is that another kind of supplier suits your project better, we will say so.